| Filed Application with National Energy Board (NEB) | May 2006 |
| NEB Public Hearing | November 2006 |
| NEB Environmental Report | April 2007 |
| NEB Decision & Issue of Project Certificate | June 2007 |
| Project Opportunities Information Sessions | June 19-21, 2007 |
| Consultation & Communication | Ongoing |
| | - Brunswick Pipeline Commitments (PDF, 145 Kb) | Filed July 5, 2007 |
| | - Public Consultation Plan | Filed August 16, 2007 |
| Field Work and Environmental Planning | Ongoing |
| - Environmental Protection Plan Filed | August 31, 2007 |
| Landowner Discussions/Easement Acquisition | Ongoing |
| Filed Proposed Detailed Route | July/August 2007 |
| | - Resolution of Routing Issues | July - November 2007 |
| | - Detailed Route Public Open Houses (PDF, 258 Kb) | September 10-13, 2007 |
Rockwood Park Construction & Restoration Plan Consultation (PDF, 221 Kb) | June - November 2007 |
| Pipeline Construction | November 2007 - November 2008 |
| | - Begin Clearing | November 2007 |
| | - Begin Grading and Trenching | December 2007 |
| | - Arrival of Pipe Sections | January 2008 |
| | - Begin Lowering in/Installation of Pipe | January 2008 |
| | - Horizontal Directional Drill (HDD) under the St. John River | Winter 2008 |
| | - Right of Way Restoration | Fall 2008 |
| Target In-Service | November 2008 |